Construction Updates - Active Projects
 New Eldorado Parkway Interchange is Open
The Texas Department of Transportation (TxDOT) has opened the new Eldorado Parkway Interchange, however some work is still needed for the interchange to be fully complete. Drivers will notice the u-turns currently have stop signs but they will soon have dedicated signals. Additional pavement markings, signs, and concrete sidewalks are also needed. In the coming days and weeks, additional lane closures will be required to complete the work. Drivers are encouraged to pay close attention to pavement markings, signs, and signals as they travel through the intersection.

Residents are encouraged to familiarize themselves with the unique operation of this intersection. It is what’s called a Single Point Urban Interchange (SPUI). The name refers to the fact that all traffic turning left to/from U.S. 75 will be controlled from a single set of traffic signals located directly atop the bridge. This allows left-turning vehicles to turn simultaneously without crossing. See the video at the right.
There will be three different traffic cycles:
  • The first is for Eldorado Parkway through traffic that is not turning.
  • The second is for traffic turning left from U.S. 75 onto Eldorado Parkway.
  • The third is for traffic turning left from Eldorado Parkway onto U.S. 75.

Closure Notices
   More Information    Construction Updates
 Active Projects

U.S. 75 Reconstruction - S.H. 121 to White Ave.
 U.S. 75 Reconstruction - S.H. 121 to U.S. 380 Details  
Redbud Blvd. Realignment
 Redbud Blvd. Realignment  Details
  • Realign the roadway starting at the former Blockbuster site north to intersect with Bloomdale Rd. at Shawnee Dr.
  • Two lanes of the ultimate four-lane roadway are being constructed
  • Existing Redbud Blvd. will tie into new roadway
  • Construction is scheduled to be complete in the fall of 2015.
  • Project Contact - Joshua Cotton, PE, 972-547-7423
U.S. 380 Access Management Study -            
Coit Rd. to Hardin Blvd.
 US 380 Access Management Study Details            
Project Timeline
  • Fall 2014: Data Gathering
  • Jan. - Feb. 2015: Development of Preliminary Plan
  • Feb. 18, 2015: Review of plan by Development Advocacy Group
  • April 1, 2015: Public Meeting
  • April - May 2015: Present draft plan during City Council Workshop
  • July - August 2015: Review of draft document by public, council and TxDOT
  • December 2015: Request adoption by ordinance during City Council meeting

Lake Forest Dr. Lanes 5 & 6
 Lake Forest Dr. Lanes 5 and 6


  • Widen Lake Forest Dr. from S.H. 121 to McKinney Ranch Pkwy. from four lanes to six lanes.
  • The project is scheduled to begin construction in November 2015 and be completed by June 2016. 
  • Project Contact - Blake Sills, PE, 972-547-3489